February 25–27, 2016
The Board of Trustees approves the proposed Community Center with Dining project.
May 31, 2016
Construction begins after Commencement and Reunion.
June–August 2016
Blanchard renovation phase 1: closed for summer.
Blanchard to reopen in late August, 2016.
September 2016–December 2017
Construction of dining addition.
- Completion of steel Installation: mid March, 2017
- Concrete slab pour: mid April, 2017
- Masonry work commences: mid May, 2017
June–November 2017
Blanchard renovation phase 2: closed for summer.
Blanchard to reopen in late August, 2017.
- Renovations commence on floors 2 & 3: early June, 2017
- Floors 2 & 3 open for occupancy: mid August, 2017
- Substantial completion of addition: late November, 2017
January 2018
Projected opening of Community Center (top two levels only) and new dining addition.
December 2017–March 2018
Blanchard renovation phase 3: lower level closed, beginning with December recess.
- Renovations commence on floor 1: late December, 2017
- Relocation of existing kitchen equipment commences: late December, 2017
April 2018
Substantial completion of renovations.