Construction Timeline

February 25–27, 2016

The Board of Trustees approves the proposed Blanchard Community Center project.

May 31, 2016

Construction begins after Commencement and Reunion.

June-August 2016

Blanchard renovation phase 1: closed for summer.
Blanchard to reopen in late August 2016.

September 2016-December 2017

Construction of dining addition.

June-August 2017

Blanchard renovation phase 2: closed for summer.
Blanchard to reopen in late August 2017.

January 2018

Projected opening of Blanchard Community Center (top two levels only) and new dining addition.

December 2017–March 2018

Blanchard renovation phase 3: lower level closed, beginning with December recess.

March 2018

Projected opening of Blanchard lower level.